The Betierra I, II and III solar power plants of Sonnedix, of 50 MW each, built by Eiffage Energía Sistemas in Belinchón, Cuenca, have just been opened.
The event was attended by the Minister for Sustainable Development for the Government of Castilla-La Mancha, Mercedes Gómez, and several colleagues from Eiffage Energía Sistemas, including Daniel Garrido, International and Renewable Energy Director; José Ignacio Rodríguez, Solar Construction Director; José David Guerra, Construction Projects Director; and Matías Gotor, Renewable Energy Business Development Manager.



BOS Contract
The scope of Eiffage Energía Sistemas’ work includes the engineering, execution of works, supply of the tracker structure, assembly and commissioning of the Betierra I, II and III photovoltaic plants, totalling 150 MW, on a surface area of almost 300 hectares.
Framework agreement with Sonnedix
Sonnedix, a leading renewable energy producer with more than 3.5 GW of operational capacity, signed its first Engineering Procurement Construction (EPC) Framework Agreement with Eiffage in March this year.
Under this framework agreement, construction activities for Sonnedix’s portfolio of projects in Spain, Italy and Portugal will be carried out under standardised general terms and conditions, which will apply to all future EPC agreements with Eiffage Energía Sistemas. Across these markets, Sonnedix currently has 650MW of renewable energy projects under construction and an additional development pipeline of 2.4 GW.
The Framework Agreement, which covers legal, technical and commercial terms and conditions, allows Sonnedix to be more streamlined and efficient in its operations. Sonnedix will be able to streamline and optimise its growth and portfolio conversion by reducing the amount of time and resources spent on securing separate EPC agreements, which can take two to three months to close.